    Miscellaneous Orders
    Title Date View / Download
    Petition for determination of Project Specific Tariff for Kaliganga-II (2×2.25 MW) Small Hydro Power Station of UJVN Ltd. under Sections 62(1)(a) and 86(1)(a) of the Electricity Act, 2003 28/04/2026
    Accessible Version : View(222 KB)
    Investment Approval for DPR of “Increasing capacity of 220 kV Substation SIDCUL, Haridwar from 2×80 (132/33 kV) MVA transformer to 3 X 80 (132/33 kV) transformer”. 13/04/2026
    Accessible Version : View(262 KB)
    Application seeking approval of Hon’ble Uttarakhand Electricity Regulatory Commission (UERC) for the investment on the additional projects sanctioned under REVAMPED DISTRIBUTION SECTOR SCHEME (RDSS) 07/04/2026
    Accessible Version : View(704 KB)
    Determination of additional surcharge in accordance with the provisions of UERC (Terms and Conditions of intra–State Open Access) Regulations, 2015 to meet the fixed cost of UPCL 30/03/2026
    Accessible Version : View(245 KB)
    Investment Approval for DPR of “Replacement of old ACSR Panther Conductor with HTLS Conductor of 132 kV Bhupatwala-T Point-Chilla-Rishikesh Line”. 23/03/2026
    Accessible Version : View(298 KB)
    Investment Approval for procurement, installation, testing & commissioning of 01 no. 80 MVA transformer & it’s associated work at 132 kV substation Jwalapur”. 19/03/2026
    Accessible Version : View(287 KB)
    Application seeking approval of the Fuel and Power Purchase Cost Adjustment (FPPCA) charged from/refunded to the consumers against the incremental power purchase cost for the quarter ending 26/02/2026
    Accessible Version : View(229 KB)
    Investment Approval for revised DPR of “Augmentation of 132 kV S/s Majra from 3×40 MVA T/F to 2×40 + 1×80 MVA T/F at 132 kV Substation, Majra, Dehradun”. 03/02/2026
    Accessible Version : View(237 KB)
    Investment Approval for revised DPR of “Supply, Erection, Testing and commissioning of 220 kV Hybrid Bay for 220 kV Piran Kaliyar-Puhana Ckt-III at 220 kV Substation Piran Kaliyar (Imlikhera)”. 02/02/2026
    Accessible Version : View(269 KB)
    Investment Approval for revised DPR of “Increasing Transformer Capacity from 3×40 MVA to 1×40 MVA + 2×80 MVA at 132 kV Substation Bhupatwala”. 12/01/2026
    Accessible Version : View(251 KB)
    Petition for seeking prior approval of Capital Investment for Rehabilitation works of Head Race Tunnel (HRT) of Maneri Bhali-II, HEP, Distt- Uttarkashi 08/01/2026
    Accessible Version : View(388 KB)
    Suo-moto proceedings in the matter of removal of difficulties under UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy 06/01/2026
    Accessible Version : View(174 KB)
    Application seeking approval for investment on the following projects: (a) Construction of new 2×5 MVA, 33/11 kV S/s at Pakhi, District-Chamoli along with its associated 33 kV & 11 kV lines. 29/12/2025
    Accessible Version : View(249 KB)
    Petition seeking adoption of Tariff for the procurement of 500 MW Round the Clock (RTC) coal-based power through tariff-based competitive bidding process on a medium-term basis for a period of 4 years 17/12/2025
    Accessible Version : View(286 KB)
    Petition for seeking prior approval of Capital Investment for Strengthening of Bridges and service road along power channel from Dakpathar Barrage to Kulhal 08/12/2025
    Accessible Version : View(504 KB)
    Investment Approval for “Termination of the LILO of 220 kV Sherpur-Jhajra at 120 MW Vyasi HEP (UJVNL) for direct connection at 400 kV substation Sherpur (PGCIL) 08/12/2025
    Accessible Version : View(273 KB)
    Investment Approval for DPR of “Augmentation of Transformation Capacity from 2×160 MVA (220/132 kV) to 3×160 MVA (220/132 kV) by Supply 02/12/2025
    Accessible Version : View(174 KB)
    Application seeking approval for the additional investment on Cyber Security and GIS Components, in ongoing IT/OT work sanctioned under RDSS 27/11/2025
    Accessible Version : View(415 KB)
    Suo-moto proceeding initiated by the Commission in the matter of Show Cause Notice under Section 142 of the Electricity Act, 2003, read with Regulation 3.3.2(4) of the UER 25/11/2025
    Accessible Version : View(386 KB)
    Misc. Application filed by Shri Vikram Singh Chikara, Kuanwala, Near Soap Factory/Generator Factory, Dehradun pertaining to Shifting of Electric Line. 24/11/2025
    Accessible Version : View(159 KB)
    Review Petition under Section 94(1)(f) of the Electricity Act, 2003 read with Regulation 54 of UERC (Conduct of Business) Regulations, 2014 w.r.t. seeking review of the Order dated 07.10.2024 21/11/2025
    Accessible Version : View(147 KB)
    Application seeking approval of the Fuel and Power Purchase Cost Adjustment (FPPCA) charged from/refunded to the consumers against the incremental power purchase cost for the quarter ending June 18/11/2025
    Accessible Version : View(203 KB)
    Investment Approval for DPR of “Construction of 400/220 kV GIS Substation, Roorkee along with Construction of LILO of 400 kV Puhana (Roorkee)-Muzaffarnagar Line at proposed 400 kV substation Roorkee 10/11/2025
    Accessible Version : View(692 KB)
    Suo-motu proceedings in the matter of in-principle approval sought by Uttarakhand Power Corporation Limited for procurement of 500 MW Round the Clock power against Medium Term tender invited by it. 06/11/2025
    Accessible Version : View(1 MB)
    Suo-moto proceedings in the matter of Public Notice issued inviting comments in the matter of requests made by the Solar Power Plant Developers for extension of Scheduled Commercial Operation Date 06/11/2025
    Accessible Version : View(181 KB)
    Suo-moto proceedings in the matter of implementation of Hon’ble APTEL’s Judgement dated 30.05.2025 in Appeal No. 259 of 2017 and IA no. 718 of 2024. 17/10/2025
    Accessible Version : View(286 KB)
    Investment Approval for DPR of “Augmentation of 132 kV S/s Laksar from 3×40 MVA Transformer to 2×40 MVA+1×80 MVA Transformer”. 13/10/2025
    Accessible Version : View(211 KB)
    Investment Approval for DPR of “Ampacity enhancement of 220 kV Puhana-Roorkee Line with HTLS Conductor”. 13/10/2025
    Accessible Version : View(217 KB)
    Petition seeking review of the Order dated 13.05.2025 passed by the Commission in the Suo-moto proceedings in the matter of implementation of the Hon’ble APTEL’s 06/10/2025
    Accessible Version : View(534 KB)
    Determination of additional surcharge in accordance with the provisions of UERC (Terms and Conditions of intra–State Open Access) Regulations, 2015 03/10/2025
    Accessible Version : View(209 KB)
    Investment Approval for DPR of “Replacement of old Panther Conductor with HTLS Conductor of 132 kV Majra-Jhajra line” 26/09/2025
    Accessible Version : View(128 KB)
    Petition seeking review of the Tariff Order dated 11.04.2025 on the approval of Business Plan and MYT for fifth Control Period from FY 2025-26 to FY 2027-28 and tariff determination 04/09/2025
    Accessible Version : View(826 KB)
    Petition seeking removal of certain difficulties/relaxation in Implementation of Tariff Order dated 11.04.2025 passed by the Commission in exercise of its power u/s 64(1) read with Section 61 and 62 03/09/2025
    Accessible Version : View(655 KB)
    Application seeking approval of the Fuel and Power Purchase Cost Adjustment (FPPCA) charged from/refunded to the consumers against the incremental power purchase cost for the quarter ending March 20/08/2025
    Accessible Version : View(238 KB)
    Review of the Benchmark Capital Cost for Solar PV, Solar Thermal and Grid Interactive Rooftop & Small Solar PV Plants to be applicable for FY 2025-26 and onwards till reviewed/ revised 20/08/2025
    Accessible Version : View(295 KB)
    Petition for grant of relaxation in clause 2.4 (vii) of the Commission Investment Approval Order dated 16.08.2024 in Petition No. 37 of 2024 regarding “Construction of 220/33 kV GIS substation 12/08/2025
    Accessible Version : View(174 KB)
    Investment Approval for DPR of “Augmentation of Transformer Capacity at 220 kV S/s SIDCUL Haridwar from 2×80 MVA (132/33 kV) + 1×50 MVA (220/33 kV)+1×25 MVA (220×33 kV) to 2×80 MV 30/07/2025
    Accessible Version : View(192 KB)
    Application seeking approval for the investment on the project for “Installation of LT Capacitor Banks on Distribution Transformers in the State of Uttarakhand.” 28/07/2025
    Accessible Version : View(450 KB)
    Petition seeking review of the Commission’s Order dated 27.03.2025, passed in the Suo-Moto proceedings regarding extension request for development and commissioning 21/07/2025
    Accessible Version : View(254 KB)
    Petition regarding permission to install Grid Interactive Rooftop Solar PV Plant beyond 1.0 MW limit set by the Commission with Net Metering facility by UPCL. 08/07/2025
    Accessible Version : View(201 KB)
    Petition seeking review of the Commission’s Order dated 11.04.2025 on the determination of Annual Fixed Charges for FY 2025-26 alongwith truing up of FY 2023-24 of M/s SEPL. 20/06/2025
    Accessible Version : View(199 KB)
    Petition for seeking prior approval of capital investment for Augmentation of transformer capacity of 132 /33 kV substation of Sharda Power House 06/06/2025
    Accessible Version : View(262 KB)
    Application seeking approval of the Fuel and Power Purchase Cost Adjustment (FPPCA) charged from/refunded to the consumers against the incremental power purchase cost. 22/05/2025
    Accessible Version : View(227 KB)
    Application seeking approval of the Commission on the Draft Power Purchase Agreement for short term between Uttarakhand Power Corp. Ltd. 20/05/2025
    Accessible Version : View(166 KB)
    Application seeking approval of the Commission on the Draft Power Purchase Agreement for short term between Uttarakhand Power Corp. Ltd. and M/s Arunachal Pradesh Power Corporation Pvt. Ltd. 20/05/2025
    Accessible Version : View(166 KB)
    Petition for Investment Approval for Revised DPR of “Procurement of 500 MVA 400/220 kV transformer along with NIFPES & construction of 400 kV and 220 kV (AIS) bays. 19/05/2025
    Accessible Version : View(152 KB)
    Petition for Investment Approval for Revised DPR of “Procurement of 500 MVA 400/220 kV transformer 19/05/2025
    Accessible Version : View(152 KB)
    Application seeking approval of the Commission for deviation/modification and/or clarification in specific clauses of the bidding documents (RFQ, RFP, and APP) issued for procurement of 500 MW RTC. 15/05/2025
    Accessible Version : View(172 KB)
    Filing of Miscellaneous Petition u/s 181(1) r/w Section 181(2)(zp) r/w Section 94(1)(f) of the Indian Electricity Act, 2003, seeking relaxation of Clause 2.1(4) 15/05/2025
    Accessible Version : View(240 KB)
    Suo-moto proceedings in the matter of implementation of Hon’ble APTEL’s Judgement dated 28.08.2024 in Appeal No. 100 of 2017 and Appeal no. 389 of 2018.. 13/05/2025
    Accessible Version : View(355 KB)
    Application seeking approval of the Commission for deviation/modification and/or clarification in specific clauses of the RFQ issued for procurement of 1320 MW RTC coal-based power under Long-Term. 09/05/2025
    Accessible Version : View(133 KB)
    Petition under Section 61, 62 & 86 of the EA, 2003 read with Regulation 50(6) of the UERC (Terms & Conditions for Determination of Multi Year Tariff) Regulations, 2018 & 2021 09/05/2025
    Accessible Version : View(310 KB)
    Additional security deposit amount levied 3 times of fortnightly bill by Uttarakhand Power Corporation Limited from April 2024 onwards in monthly electricity bills being issued. 08/05/2025
    Accessible Version : View(209 KB)
    Additional security deposit amount levied 3 times of fortnightly bill by Uttarakhand Power Corporation Limited from April 2024 onwards in monthly electricity bills being issued. 08/05/2025
    Accessible Version : View(171 KB)
    Additional security deposit amount levied 3 times of fortnightly bill by Uttarakhand Power Corporation Limited from April 2024 onwards in monthly electricity bills being issued. 08/05/2025
    Accessible Version : View(208 KB)
    Application seeking approval for the investment on the following projects: (1) Construction of 33/11 kV Substation alongwith its associated 33 kV line at Kathgodam, Haldwani, District-Nainital. 30/04/2025
    Accessible Version : View(297 KB)
    Application seeking approval of the Commission on Draft Power Purchase Agreement between Uttarakhand Power Corporation Ltd. and M/s Rai Bahadur Narain Singh Sugar Mills Ltd. – 30 MW (Surplus 19.1 MW 30/04/2025
    Accessible Version : View(131 KB)
    Determination of additional surcharge in accordance with the provisions of UERC (Terms and Conditions of intra–State Open Access) Regulations, 2015 to meet the fixed cost of UPCL 08/04/2025
    Accessible Version : View(165 KB)
    Suo-moto proceedings in the matter of time extension in Scheduled Commissioning Date of Solar PV Plants to be developed by various developers in the State of Uttarakhand. 27/03/2025
    Accessible Version : View(169 KB)
    Petition for Investment Approval for “Replacement of old 132/33 kV 20 MVA Transformer with new 132/33 kV 20 MVA Transformer at 132 kV Substation Ranikhet under O&M Division Almora.” 27/03/2025
    Accessible Version : View(207 KB)
    Petition for Investment Approval for “Supply & erection of Substation Automation System (SAS) at 220/33 kV Substation Jafarpur and 220/132/33 kV Substation Kamaluaganja” 24/03/2025
    Accessible Version : View(215 KB)
    Application seeking approval for the investment w.r.t. Construction of 33/11 kV Substation at Shri Kedarnath Dham at District-Rudraprayag. 24/03/2025
    Accessible Version : View(364 KB)
    Review of UERC Order dated 30.09.2024 with regard to “Determination of Additional Surcharge in accordance with the provisions of UERC (Terms and Conditions of Intra-State Open Access) Regulations,2015 12/03/2025
    Accessible Version : View(165 KB)
    Application seeking approval of the Fuel and Power Purchase Cost Adjustment (FPPCA) charged from/refunded to the consumers against the incremental power purchase cost for the quarter ending Sept,2024. 11/03/2025
    Accessible Version : View(218 KB)
    Suo-moto proceedings initiated by the Commission in the matter of Noncompliance of the sub-Regulations 3.3.3(15), 3.3.3(16), 3.4.3(10) & 3.4.3(11) of the UERC 10/03/2025
    Accessible Version : View(141 KB)
    Investment Approval for DPR of “Augmentation of 132 kV S/s Purkul, Dehradun from 100 MVA (2×40 MVA + 1×20 MVA) to 120 MVA (3×40 MVA) transformer at 132/33 kV Voltage level.” 10/02/2025
    Accessible Version : View(72 KB)
    Petition for Investment Approval of Revised DPR of “Construction of 132 kV Bindal–Purkul Transmission Line including underground cabling work between tower No. 47 and 50. 24/01/2025
    Accessible Version : View(207 KB)
    Petition for Investment Approval for “Augmentation of Transformation capacity from 2×40 MVA (132/33 KV) to 3×40 MVA (132/33 KV) by procurement, installation, testing & commissioning 22/01/2025
    Accessible Version : View(233 KB)
    Petition seeking approval of the Commission for Advance & Return Energy Banking to M/s Uttar Pradesh Power Corporation Limited under an Energy Banking 06/01/2025
    Accessible Version : View(151 KB)
    Petition seeking Approval of Releasing of Additional 2000 kVA Load (Total Contracted Load of 12000 kVA) on a Supply Voltage Line of 33 kV and thereby providing relaxation over Regulation 24/12/2024
    Accessible Version : View(220 KB)
    Application seeking approval of the Fuel and Power Purchase Cost Adjustment (FPPCA) charged from/refunded to the consumers against the incremental power purchase cost for the quarter ending June, 2024 09/12/2024
    Accessible Version : View(182 KB)
    Petition seeking prior approval of the Commission for Advance & Return Energy Banking to M/s Haryana Power Purchase Centre under an Energy Banking Agreement with Uttarakhand Power Corporation Ltd. 22/11/2024
    Accessible Version : View(157 KB)
    Petition seeking approval of capital investment on Rehabilitation works of civil structure of Ichari Dam under Section 61 and 86 of the Electricity Act, 2003 read with the relevant regulations and 21/11/2024
    Accessible Version : View(371 KB)
    Hon’ble APTEL’s Judgement dated 19.07.2024 on Appeal no. 215 of 2016, Appeal No. 283 of 2016 & Appeal No. 139 of 2018 w.r.t. ‘Denial of 50% of the excess IDC and 50% of Price Variation component 20/11/2024
    Accessible Version : View(333 KB)
    Review of the Benchmark Capital Cost for Solar PV, Solar Thermal and Grid Interactive Rooftop & Small Solar PV Plants to be applicable for FY 2024-25 19/11/2024
    Accessible Version : View(350 KB)
    Petition for fixation of voltage wise distribution loss or reduction of approved distribution loss for open access captive solar power plants under Uttarakhand State Solar Policy-2023. 28/10/2024
    Accessible Version : View(187 KB)
    Suo-moto proceeding in the matter of tariff of RE Component in addition to the tariff applicable for Rajwakti Small Hydro Plant of M/s Him Urja Pvt. Ltd. 16/10/2024
    Accessible Version : View(152 KB)
    Application seeking review of the UERC’s Tariff Order on True-up for FY 2022-23, Annual Performance Review for FY 2023-24 and Annual Fixed Charges for FY 2024-25. 10/10/2024
    Accessible Version : View(204 KB)
    Application seeking approval of the Commission on the Draft Power Purchase Agreement for short term between Uttarakhand Power Corp. Ltd. and M/s Arunachal Pradesh Power Corporation Pvt. Ltd. (APPCPL) 08/10/2024
    Accessible Version : View(153 KB)
    Petition filed under Regulation 9, 20, 58, 59, 61 and 62 of the UERC (Conduct of Business Regulations), 2014 and Regulations 3.6 and chapter-8 Regulation 1 to 3 of UERC Supply Code Regulation 2020 07/10/2024
    Accessible Version : View(233 KB)
    Application for Determination of Additional Surcharge in accordance with the provisions of UERC (Terms and Conditions of Intra-State Open Access) Regulations, 2015 to meet the fixed cost of UPCL 30/09/2024
    Accessible Version : View(186 KB)
    Application seeking removal of difficulty/clarification in the UERC (The Electricity Supply Code, Release of New Connections and Related Matters) Regulations, 2020. 23/09/2024
    Accessible Version : View(205 KB)
    Application seeking approval of the Commission on the Draft Power Purchase Agreement between Uttarakhand Power Corporation Limited and M/s JGN Sugar and Biofuels Pvt. Ltd. 19/09/2024
    Accessible Version : View(163 KB)
    Review Petition to relax/waive or vary the provisions of UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2007 and UERC (Release of New LT Connections 18/09/2024
    Accessible Version : View(238 KB)
    Investment Approval for Augmentation of 220 kV substation Jhajra (2×160 MVA to 3×160 MVA T/F at 220/132 kV voltage level and 2×80 MVA to 3×80 MVA at 132/33 kV voltage level). 17/09/2024
    Accessible Version : View(110 KB)
    Application seeking approval of the Fuel and Power Purchase Cost Adjustment (FPPCA) charged from/refunded to the consumers against the incremental power purchase cost for the quarter ending March 10/09/2024
    Accessible Version : View(217 KB)
    Application seeking approval of the Fuel and Power Purchase Cost Adjustment (FPPCA) charged 09/09/2024
    Accessible Version : View(217 KB)
    Application seeking approval of the Commission on the Draft Power Purchase Agreement for short term between Uttarakhand Power Corp. Ltd. and M/s Tata Power Trading Company Ltd. 08/09/2024
    Accessible Version : View(148 KB)
    Application seeking approval for the investment on the project for “Installation of Automatic Reactive Power Solution (Capacitor Bank) on 33/11 kV Substations in the State of Uttarakhand.” 02/09/2024
    Accessible Version : View(431 KB)
    Investment Approval for Construction of proposed 220/132/33 kV S/s Raipur (Bhagwanpur), Roorkee along with construction of associated lines (220 kV D/c Line from 400 kV substation, Puhana (PCGIL) 02/09/2024
    Accessible Version : View(278 KB)
    Review Petition filed by Power Transmission Corporation of Uttarakhand Limited against the Commission’s Order dated March 28, 2024 in Pet. No. 49 of 2023 in the matter of truing up for FY 2022-23, 21/08/2024
    Accessible Version : View(331 KB)
    I. Construction of 220/132/33 kV GIS substation Banbasa, Tanakpur. 16/08/2024
    Accessible Version : View(247 KB)
    Investment Approval for Procurement 01 Set of Emergency Restoration System (ERS) for Transmission Lines of PTCUL. 14/08/2024
    Accessible Version : View(199 KB)
    Petition filed under Section 86 of Electricity Act 2003, Regulation 45 of Uttarakhand Electricity Regulatory Commission (Conduct of Business) Regulations, 2014 and keeping in view relevant provisions 30/07/2024
    Accessible Version : View(222 KB)
    Application seeking review of the UERC’s Tariff Order on True-up for FY 2022- 23, Annual Performance Review for FY 2023-24, and Annual Fixed Charges for FY 2024-25. 30/07/2024
    Accessible Version : View(128 KB)
    Petition under Section 86 (1)(f) and 86 (1)(k) of the Electricity Act, 2003 read with Article 8, 10, 12 and 13 of the Power Purchase Agreement dated 18.02.2021 executed between Bhilangan 22/07/2024
    Accessible Version : View(101 KB)
    Petition for resolution of matter pertaining to “Compensation for Delayed Payment of Invoices” for power supplied to Uttarakhand Power Corporation Limited (UPCL) from 214 MW (225 MW) ISO for Phase I 12/07/2024
    Accessible Version : View(225 KB)
    Inherent power of the Commission to amend certain provision of the Uttarakhand Electricity Regulatory Commission (Terms and Conditions for Determination of Multi Year Tariff) Regulations, 2021. 27/06/2024
    Accessible Version : View(85 KB)
    CORRIGENDUM Dated: July 12, 2024 Reference: Order dated June 27, 2024 in the matter of Inherent power of the Commission to amend certain provision of the Uttarakhand Electricity Regulatory Commission 27/06/2024
    Accessible Version : View(74 KB)
    Inherent power of the Commission to amend certain provision of the Uttarakhand Electricity Regulatory Commission (Terms and Conditions for Determination of Multi Year Tariff) 27/06/2024
    Accessible Version : View(85 KB)