Order on Complaint filed by Sh. Manohar Singh Rawat against Electricity Officers in Munsiyari Division and Pithoragarh
|
|
(149 KB)
|
Order on Excessive delay in release of connection of Bajpur Co-operative Sugar Factory Ltd., Bajpur, Udham Singh Nagar
|
|
(291 KB)
|
Order on Intervener Application of M/s Swastik Solvent Products (India) Ltd., District-Rampur and in the matter of Sh. Ranjit Singh & Other Vs. UPCL & Others
|
|
(64 KB)
|
Order in the matter of Shri Ranjit Singh & Others Vs. UPCL & Others
|
|
(231 KB)
|
Order on Restriction of Over-drawal of Power by UPCL from the Grid based on the CERC (Unscheduled Interchange Charges and related matters) (Amendment) Regulations, 2010
|
|
(150 KB)
|
Order on Investment on Project covering the construction of new 33 kV Double Circuit Line from 33 kV Sub-station Ghansali to Pipaldali Junction Point including dismantling of existing single
|
|
(131 KB)
|
Order in the matter of Sh. Ranjit Singh & Other Vs. UPCL & Others
|
|
(90 KB)
|
Order in the matter of the Investment on the project covering the construction of 05 Nos. new 33/11 Substations & their associated lines
|
|
(131 KB)
|
Order in petition filed by Sh. Ranjit Singh
|
|
(85 KB)
|
Order in Complaint filed by Sh. Manohar Singh Rawat
|
|
(76 KB)
|
Order inScheduled Load Shedding
|
|
(95 KB)
|
Order in Approval of additional load of 4 MVA to Birla Tyres, Haridwar by releasing power load of 14 MVA on supply voltage of 33 kV
|
|
(108 KB)
|
Order on the matter of waiver of token penalties imposed by the Commission in the Tariff Order for the FY 2009-10 for late submission of ARR/Tariff filings by licensees and the generating company
|
|
(89 KB)
|
Order in the matter of Violation of provisions of Indian Electricity Rules, 1956 and Commission’s directions on providing proper neutral grounding, earthing and protective system
|
|
(357 KB)
|
Order on Power Cut
|
|
(3 MB)
|
Order in Determination of Final Tariff for Maneri Bhali Stage II Large Hydro Power Project u/s 62(1)(a) and 86 of the Electricity Act, 2003
|
|
(200 KB)
|
Order inApplication of Vanala Small Hydro Project of 15 MW in District Chamoli for grant of permission of Open Access for carrying electricity from Vanala SHP to outside the State of Uttarakhand
|
|
(597 KB)
|
Order inApplication of Swasti Power Engineering Limited in respect of its Bhilangana Hydro Power Project (BHPP) (3 x 7.5 MW) generating station for grant of open access for evacuation of power
|
|
(557 KB)
|
Order in Electrocution of Sh. Usman, Dehradun on 09.09.2009
|
|
(254 KB)
|
Order in Application for Approval of the Commission for the Investment on the Project covering the Construction of 16 new 33 & 11 kV Sub-Stations and their Associated Lines
|
|
(156 KB)
|
Order in One-Time Checking & Correction of Metering System of KCC Consumers and Monthly Monitoring of their Billing MRI Data
|
|
(161 KB)
|
Order inViolation of Provisions of IE Rules 1956 and Proper Neutral Grounding, Earthing and Protective System
|
|
(835 KB)
|
Order in Electrocution of Sh. Bhagwant Lal, Village- Aholi Sunar (Syali), Almora on 13-14.08.2008
|
|
(234 KB)
|
Order in Complaint filed by Shri A.S. Bisht with regard to Routing of LT Line at a very low height
|
|
(234 KB)
|
Order inComplaint filed by Shri M.S. Bisht, Haridwar and Wrong Reporting in Division Wise Monthly Report on Release of New Connections
|
|
(217 KB)
|
Order in Power Cut
|
|
(204 KB)
|
Interim Order on Vanala SHP of 15 MW for grant of permission of Open Access for carrying Electricity.
|
|
(135 KB)
|
Order on Works Charges for Enhancement or Reduction of Contracted Load for HT & EHT Connections to be charged by the Distribution Licensee
|
|
(185 KB)
|
Payment of Security Deposit and Additional Security Deposit by way of Bank Guarantee or Letter of Credit
|
|
(269 KB)
|
On Review Petition of Commission’s Order dated 18-03-2008 for FY 2007-08 & FY 2008-09
|
|
(874 KB)
|
Order onNon-compliance of Section 59 of Electricity Act, 2003 and Regulation 5 of the UERC (Standards of Performance) Regulations, 2007
|
|
(185 KB)
|
Order onfinalisation of Clause 6 of RTS-7
|
|
(337 KB)
|
Order on Earthed Terminal and Installation & Maintaining records of Test Results
|
|
(389 KB)
|
UERC’s Order on Neutral Grounding Earthing System
|
|
(1 MB)
|
UERC’s order in the matter of Show cause notice dated 05.09.2008 in the matter of non compliance of regulation of the UERC (The Electricity Supply Code) Regulations 2007
|
|
(117 KB)
|
In the matter of Complaint filed by Dr. Sarla Raman, for payment of compensation for delay in restoration of supply and replacement of burnt meter by UPCL.
|
|
(75 KB)
|
UERC’s Order on Penalties imposed by UPCL on industries for excess usage of power during the restricted period effective from 31.12.2007 to 15.02.2008.
|
|
(2 MB)
|
Commission’s order dated 30.8.2007 regarding waiver of late payment surcharge for recovery of electricity arrears outstanding against PTW consumers.
|
|
(55 KB)
|
Order on Application seeking waiver of compensation payable by UPCL as per sub-regulation (3.3.4) of regulation 3.3 of the UERC (The Electricity Supply Code) Regulations, 2007.
|
|
(79 KB)
|
Suo-moto proceedings for investigation of billing details of industrial consumers about 35 BHP of UPCL.
|
|
(73 KB)
|
Order on Power Overdraw by UPCL from grid when grid frequency is below 49.5 Hz.
|
|
(107 KB)
|
Application seeking extension of time of submission of Aggregate Revenue Requirement and Tariff Proposal for FY 2008-09
|
|
(49 KB)
|
UPCL Proposal, seeking approval of the Commission on scheduled load shedding with immediate effect in the State of Uttarakhand for the period up to 15th January, 2008.
|
|
(217 KB)
|
In the Matter of approval of Capital Investment under Para 11 of the Transmission and Bulk Supply License [License No. 1 of 2003].
|
|
(73 KB)
|
in the matter of application seeking approval of the Commission regarding introduction of Scheme of waiver of Late Payment Surcharge for recovery of electricity arrears outstanding
|
|
(95 KB)
|
Order on Show Cause Notice dated 13.04.2007 regarding supply of electricity to Industrial consumers on selective basis
|
|
(171 KB)
|
Rate of Interest payable on Security Deposit of consumers.
|
|
(94 KB)
|
No scheduled power cuts shall be allowed in the State except in the event of any direction in this regard from RLDC till concept paper is finalized.
|
|
(47 KB)
|
Application seeking review of the Commission’s Order dated 22-12-2006 imposing penalty u/s 142 of the Electricity Act, 2003 for non-compliance of Commission’s
|
|
(69 KB)
|
Application filed by Shri B.M. Verma, Chairman and Managing Director on behalf of UPCL, seeking time for complying with UERC (Release of New LT Connection Enhancement
|
|
(84 KB)
|
Non compliance of Commission’s order for ToD meter in the State and hearing in the matter held on 20.12.2006.
|
|
(118 KB)
|
Show Cause Notice dated 01.12.2006 issued to Shri B. M. Verma S/o Late Shri Walaiti Ram R/o 220, Vasant Vihar, Phase-II, Dehradun regarding non compliance of Commission’s Orders
|
|
(116 KB)
|
The Commission has decided to get the issue of defective bills, investigated through an independent expert agency under section 128 of the Electricity Act, 2003
|
|
(51 KB)
|
The Commission directs the committee and its member to ensure no delays in ongoing statutory investigation regarding some discrepancies in accounting of substantial surpluses
|
|
(6 KB)
|
show cause why action should not be initiated against it for its failure to comply with orders of the Redressal Forum dated 14/17.12.2005 for refund of excess amount realised from consumers
|
|
(11 KB)
|
Penalty imposed by UPCL and demanded by the Executive Engineer, Distribution Division (Rural) Dehradun for use of Electricity by the Petitioner during peak hours.
|
|
(19 KB)
|
Final opportunity to UJVNL to submit tariff proposals along with detailed data on its costs for Generation tariff of UJVNL’s plants.
|
|
(14 KB)
|
Detailed investigation of the issue of the surplus earned by the distribution licensee investigated under Section 128 of the Electricity Act, 2003.
|
|
(5 KB)
|
Paper on “Approach to Initial Tariff for Generating Stations with capacity upto 1 MW” circulated on 08.09.2005 and in the matter of Tariff determination for hydro generating stations
|
|
(21 KB)
|
Paper on “Approach to Initial Tariff for New Hydro Generating Stations with capacity above 1 MW and upto 25 MW” and in the matter of Tariff determination for hydro generating stations
|
|
(72 KB)
|
Show cause notice dated 30-05-2005 under sections 142 and 146 of the Electricity Act, 2003 and in the matter of Non-compliance of directions pertaining to arrangements for collection
|
|
(24 KB)
|
Non compliance by UPCL of provisions of Section 55 of the Electricity Act, 2003 and UPCL’s Application under Section 55 of the Electricity Act, 2003 dated 26.05.2005
|
|
(40 KB)
|
Reject of petitioner application of M/s Arpit Steel and others V/s UPCL.
|
|
(226 KB)
|
Admit of PTCUL’s ARR petition for FY. 2005-06.
|
|
(46 KB)
|
Admit of UPCL’s ARR petition for FY. 2005-06
|
|
(10 KB)
|
Final opportunity to UPCL to submit its ARRs and tariff proposals for the years 2004-05 and 2005-06 alongwith requisite information in accordance with the distribution and transmission
|
|
(12 KB)
|
To get a fair and accurate report on compliance of Commission’s directions listed out in Chapter-7 of the Commission’s Tariff Order dated 08.09.2003 of UPCL, Constitution of Experts Committee
|
|
(9 KB)
|
nterim Order in the matter of Wrong application of electricity tariff by UPCL to Defence Bulk Consumers and in the matter of Commander Works Engineer (Hills), Military Engineer
|
|
(10 KB)
|
UJVNL to submit its tariff proposals of 09 plants latest by 15.09.04 along with detailed data on its costs in accordance with the regulations already notified in the formats
|
|
(9 KB)
|
Recovery of charges exceeding the tariff for domestic consumers.
|
|
(10 KB)
|
in the matter of Change in the adhoc power purchase rate of 37 paise/unit fixed in Tariff order dated 8th September 2003.
|
|
(14 KB)
|
in the matter of Suomoto proceedings initiated with respect to meter reading, billing and collection from Domestic Consumers.
|
|
(41 KB)
|
in the matter of Change in the adhoc power purchase rate of 37 paise/unit fixed in Tariff order dated 8th September 2003.
|
|
(14 KB)
|
in the matter of Suomoto proceedings initiated with respect to meter reading, billing and collection from Domestic Consumers.
|
|
(41 KB)
|
in the matter of Approval of capital investment under clause 11 of Transmission and Bulk Supply Licensee and Distribution and Retail Supply License.
|
|
(22 KB)
|
in the matter of Approval of capital investment under clause 11 of Transmission and Bulk Supply Licensee and Distribution and Retail Supply License.
|
|
(22 KB)
|
in the matter of Misc. Applications No. 1 & 2 of 2004 dated 05 -04-2004 filed by Uttaranchal Jal Vidyut Nigam Ltd, Dehradun seeking recall and stay of Commission’s Order dated 19.03.2004.
|
|
(19 KB)
|
in the matter of Misc. Applications dated 15-09-2003 (No. 24/2003) and dated 29-09-2003 (No.27/2003) filed before the Commission by Uttaranchal Jal Vidyut Nigam Ltd, Dehradun.
|
|
(18 KB)
|
in the matter of Sale of electricity generated by the generating units of Uttaranchal Jal Vidyut Nigam Ltd. and which is surplus to the requirement of consumers of Uttaranchal State.
|
|
(13 KB)
|
in the matter of Approval of capital investment under para 11 of Transmission and Bulk Supply Licensee and Distribution and Retail Supply Licensee.
|
|
(21 KB)
|
Interim Order in the matter of recovery of charges exceeding the tariff for domestic consumers.
|
|
(10 KB)
|
in the matter of Levy and realization of independent feeder charges by Uttaranchal Power Corporation Ltd from M/S Ace Glass Containers Pvt. Ltd ,the petitioner.
|
|
(40 KB)
|
in the matter of Approval of capital investment under clause 11 of Transmission and Bulk Supply Licence and Distribution and Retail Supply Licence.
|
|
(17 KB)
|
Order on Late Payment Surcharge of Private Tubewell/ Pump set consumers
|
|
(12 KB)
|
Representation/Petition under Section 67(4) of the Electricity Act, 2003, in the matter of dispute regarding release of connection by UPCL to an individual consumer connected to the electrical
|
05/02/19 |
(99 KB)
|
Deployment of customised Renewable Purchase Obligation Compliance System (RPOCS) Web Tool in Uttarakhand.
|
12/14/18 |
(305 KB)
|
In the Matter of: Dispute between M/s Bhilangana Hydro Power Limited and Power Transmission Corporation of Uttarakhand Limited, regarding Late Payment
|
11/22/18 |
(126 KB)
|
In the matter of: Application seeking approval of the Fuel Charge Adjustment (FCA) to be charged from the consumers for the period from 01.10.2018 to 31.12.2018.
|
10/09/18 |
(452 KB)
|
In the matter of:Application seeking approval of the Commission on the Draft Power Purchase Agreement for short term power purchase between Uttarakhand Power Corp. Ltd.
|
10/31/18 |
(221 KB)
|
In the matter of:Petition No. 34 of 2018 Application seeking approval of the Power Purchase Agreement between Uttarakhand Power Corporation Ltd. and M/s Aglar Power Ltd. for Rayat SHP.
|
10/26/18 |
(172 KB)
|
Application seeking approval of the Fuel Charge Adjustment (FCA) to be charged from the consumers for the period from 01.07.2018 to 30.09.2018.
|
09/24/18 |
(481 KB)
|
Petition under section 94(1)(f) of the Electricity Act, 2003 read with Regulation 54 of the UERC (Conduct of Business) Regulations, 2014 for review of the Order dated 17.05.2018
|
09/17/18 |
(582 KB)
|
In the matter of: Suo-moto proceedings in the matter of Show Cause Notice issued to PTCUL under the provisions of Section 142 read with Section 149 of the Electricity Act, 2003
|
09/13/18 |
(126 KB)
|
Application seeking approval for the investment on the project covering the construction of 01 No. 66/33 kV Substation & its 0.60 Km associated 66 kV line.
|
09/12/18 |
(211 KB)
|
Application seeking permission to setup Solar Power Plant of capacity 40 MW at Haripura Dam (27.34 MW) and Tumaria Dam (13.50 MW) in District Udham Singh Nagar, Uttarakhand
|
08/29/18 |
(377 KB)
|
Application seeking approval of the Commission on the Draft Power Purchase Agreement for short term power purchase between Uttarakhand Power Corp. Ltd. and M/s Tata Power Trading Company Ltd
|
08/28/18 |
(227 KB)
|
Representation/Petition under Section 67(4) of the Electricity Act, 2003, in the matter of dispute regarding release of connection by UPCL to an individual consumer connected to the electrical network
|
12/02/19 |
(99 KB)
|
Application seeking approval of the Commission on the Power Purchase Agreement executed between Uttarakhand Power Corporation Limited and Uttarakhand
|
08/28/18 |
(329 KB)
|
Petition seeking determination of project specific tariff for 12.6 MW Small Hydro Power Project under Section 62 and 86 of the Electricity Act, 2003 read with Regulation 13
|
08/18/18 |
(781 KB)
|
Dispute between M/s Bhilangana Hydro Power Ltd and Power Transmission Corporation of Uttarakhand Limited, relating to ‘component A’ that is, regarding to transmission charges for the use.
|
12/02/19 |
(131 KB)
|