| Petition under Section 79 of the Electricity Act, 2003, read with Article 13 (“Change in Law”) of the Power Purchase Agreement (“PPA”) dated 19.03.2012 executed between M/s Uttam Sugar Mills Ltd | 30/11/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(98 KB) 
                                                         
                                                         
                                                         | 
| Petition seeking utilisation of 220 kV S/C Dedicated Transmission Line of M/s Greenko Budhil Hydro Electric Project for evacuating power from Generating Stations operating in Ravi Basin | 16/11/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(107 KB) 
                                                         
                                                         
                                                         | 
| Petition to Hon’ble Commission for resolution of matter pertaining to Deviation Settlement Mechanism (“DSM”) Claim for 214 MW (225 MW ISO) for Phase I of 2×225 MW | 12/10/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(65 KB) 
                                                         
                                                         
                                                         | 
| Review Petition for review of the Order dated 11.06.2021 passed by the Commission in Petition No. 21 of 2020 in accordance with Section 94(f) of the Electricity Act | 21/09/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(100 KB) 
                                                         
                                                         
                                                         | 
| Hon’ble APTEL’s Judgement dated 02.03.2020 in Appeal No. 18 of 2016. | 14/09/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(74 KB) 
                                                         
                                                         
                                                         | 
| Petition seeking adjustment of tariff for Vanala Small Hydro Power Project (15 MW) unit of M/s Him Urja Pvt. Ltd. in terms of the directions contained in Order of the Commission | 07/09/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(100 KB) 
                                                         
                                                         
                                                         | 
| Hon’ble APTEL’s Judgement dated 02.03.2020 in Appeal No. 18 of 2016. | 28/07/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(77 KB) 
                                                         
                                                         
                                                         | 
| Petition under Section 86(1) (c), (f) and (k) read with Section 30, Section 39(2) (c), Section 40(a) and Section 42(1) of Electricity Act, 2003 seeking directions | 15/06/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(76 KB) 
                                                         
                                                         
                                                         | 
| Petition under Section 62 and 86 of the Electricity Act, 2003 read with Regulation 1(3), 11(1) and 12 of the Uttarakhand Electricity Regulatory Commission | 23/03/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(99 KB) 
                                                         
                                                         
                                                         | 
| Interlocutory Application seeking directions to the Respondent No. 1 to maintain status quo qua 33/11 kV Darati Sub-station, thereby directing exclusive connectivity | 12/03/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(75 KB) 
                                                         
                                                         
                                                         | 
| Repeated violation of Regulation 40 of CBR, clause 11 of licence conditions and directions of the Commission issued in its various orders by UPCL. | 09/03/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(105 KB) 
                                                         
                                                         
                                                         | 
| Petition for seeking carry forward of expected surplus of 320.62 MU (non-solar) and expected deficit of 110.28 MU (Solar) Renewable Purchase Obligation of FY 2020-21 | 09/03/2021 | 
                                                         
                                                         Accessible Version :
                                                         View(97 KB) 
                                                         
                                                         
                                                         | 
| Petition for recovery of charges collected by UJVN Ltd. for supply of electricity made to the consumers of the State of Uttarakhand. | 05/01/2021 | 
                                                         