| Suo-Moto proceedings on non-compliance of Renewable Purchase Obligation (RPO) by UPCL in accordance with UERC (Compliance of Renewable Purchase Obligation) Regulations |
Accessible Version :
View(67 KB)
|
|
| Petition filed under Regulation 27(2) and 41 of the UERC (Terms and Conditions of Intra-State Open Access) Regulations, 2015 read with Regulations 59 of UERC (Conduct of Business) Regulations |
Accessible Version :
View(73 KB)
|
|
| Petition for seeking carry forward of Renewable Purchase Obligation of FY 2014-15 amounting to 526.8 MU (Non-Solar) and 2.5 MU (Solar) as per the provisions of UERC |
Accessible Version :
View(65 KB)
|
|
| Investment Approval for increasing capacity of 220 kV Sub-station Chamba from 2×25 MVA (220/33kV) to 1×50 MVA +1×25 MVA (220/33 kV). |
Accessible Version :
View(66 KB)
|
|
| Petition under Sections 62 and 86(1)(a) of the Electricity Act, 2003 read with the relevant provisions of UERC (Terms & Conditions for Determination of Tariff) Regulations |
Accessible Version :
View(324 KB)
|
|
| System strengthening of 132 kV S/s Kichha Comprising |
Accessible Version :
View(67 KB)
|
|
| Prior approval of ‘Capital Investment for Renovation & Modernization’ of Dhalipur (3×17 MW) HEP of UJVN Ltd. |
Accessible Version :
View(68 KB)
|
|
| Petition for review of the Hon’ble UERC’s order dated 30.07.2015 on “Petition for prior approval of Capital Investment for Renovation & Modernization of 3 x 30 MW MB-I HEP of UJVN Ltd”. |
Accessible Version :
View(66 KB)
|
|
| Investment Approval for Augmentation of 220 kV Substation Jhajhra from 2×40 MVA to 2×80 MVA. |
Accessible Version :
View(65 KB)
|
|
| Investment Approval for Augmentation of Transformer capacity of 132 kV substation Bhupatwala Haridwar from 2×40 MVA to 3×40 MVA by procurement, erection & commissioning |
Accessible Version :
View(66 KB)
|
|
| Investment Approval for Increasing capacity of 220 kV Substation Virbhadra Rishikesh from 2×160 MVA (220/132 kV) to 3×160 MVA (132/33 kV). |
Accessible Version :
View(65 KB)
|
|
| Petition for Review of the UERC’s Order dated 11.04.2015 on “True-up of FY 2013-14, Annual Performance Review for FY 2014-15 and Annual Fixed Charges for FY 2015-16 for UJVN Ltd”. |
Accessible Version :
View(67 KB)
|
|
| Review filed by UJVN Ltd. on Commission’s Order dated 13.03.2015 issued in the matter of prior approval of Capital Investment for Renovation & Modernization of 3×10 MW Kulhal HEP. |
Accessible Version :
View(66 KB)
|
|
| Application seeking approval of the Fuel Charge Adjustment (FCA) to be charged from the consumers for the period from 01.10.2015 to 31.12.2015. |
Accessible Version :
View(227 KB)
|
|
| Application seeking approval of UERC on the Draft Power Purchase Agreement between UPCL & M/s Greenko Budhil Hydro Power Pvt. Ltd. |
Accessible Version :
View(86 KB)
|
|
| Application seeking approval of the Commission on the Draft Power Purchase Agreement between UPCL & M/s GMR Chhattisgarh Energy Ltd. |
Accessible Version :
View(84 KB)
|
|
| Petition seeking the approval of the Commission for advance banking of power by the UPCL from Haryana Power Purchase Centre/Northern Region Utility, through a trader |
Accessible Version :
View(226 KB)
|
|
| Petitions filed under section 61 and 86 of the Electricity Act, 2003 read with the relevant regulations and guidelines of the Commission by UJVN Ltd. for approval of Capital investment |
Accessible Version :
View(54 KB)
|
|
| Petition filed under Regulation 27(2) and 41 of the UERC (Terms and Conditions of Intra-state open access) Regulations, 2015 read with Regulation 59 of UERC (Conduct of Business) Regulations |
Accessible Version :
View(64 KB)
|
|
| Petition seeking adjustment of Tariff for Motighat SHP (5 MW) due to Additional Capitalization incurred on account of damages due to natural calamity as per UERC Tariff Regulations, 2010. |
Accessible Version :
View(233 KB)
|
|
| Application seeking approval of the Commission on the Power Purchase Agreement between UPCL and Generators. |
Accessible Version :
View(231 KB)
|
|
| Petition under Section 86(1)(f) of the Electricity Act, 2003 for adjudication of the disputes between M/s Swasti Power Ltd. and Uttarakhand Power Corporation Ltd. |
Accessible Version :
View(56 KB)
|
|
| Petition under “UERC (RE) Regulations, 2008” for relief against excess rebate deduction from payment of monthly energy bill of M/s RBNS Sugar Mills Ltd., Laksar, Haridwar by UPCL. |
Accessible Version :
View(77 KB)
|
|
| Application seeking approval of the Fuel Charge Adjustment (FCA) for the quarter ending June, 2015 and to adjust the same in the FCA computation for the quarter ending September, 2015. |
Accessible Version :
View(226 KB)
|
|
| Investment approval for strengthening of 132 kV network (A) Extension of 220 kV substation Piran Kaliyar (B) Construction of 132 kV LILO of Bhagwanpur- Chudiyala. |
Accessible Version :
View(50 KB)
|
|
| Investment approval for construction of 220 kV Pirankaliyar-Puhana (PGCIL) Line. |
Accessible Version :
View(48 KB)
|
|
| Revision filed under Rule 3 Sub-Rule (3) of The Work of Licensee Rule 2006 on the Order dated 02.05.2015 issued by the District Magistrate Udhamsingh Nagar (Uttarakhand) |
Accessible Version :
View(78 KB)
|
|
| Grid connectivity for 12.6 MW SHP of M/s Uttar Bharat Hydro Power Pvt. Ltd., New Delhi(Suo-moto). |
Accessible Version :
View(65 KB)
|
|
| Compliance of Commission’s orders dated 07.11.2014 and 10.02.2015 in the matter of approval of Power Purchase Agreements between UPCL and Generators. |
Accessible Version :
View(235 KB)
|
|
| Application seeking approval of the Commission on the PPAs between UPCL and 08 nos. Generators. |
Accessible Version :
View(152 KB)
|
|
| Implementation of Retail Tariff Order issued by the Commission on 11.04.2015. |
Accessible Version :
View(228 KB)
|
|
| Petition under Section 30, 42(2), 42(3) and 86(1)(c) of the Electricity Act, 2003 read with Regulation 41 of Uttarakhand Electricity Regulatory Commission |
Accessible Version :
View(53 KB)
|
|
| Petition seeking extension of generic tariff prescribed under the UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) |
Accessible Version :
View(149 KB)
|
|
| Misc. Petition under “UERC (Tariff & Other Terms for Supply of Electricity from NRE Sources) Regulation 2008” for relief against Excess Rebate deduction from payment of Monthly Energy Bill |
Accessible Version :
View(236 KB)
|
|
| Application seeking approval of the Fuel Charge Adjustment (FCA) to be charged from the consumers for the period from 01-04-2015 to 30-06-2015. |
Accessible Version :
View(227 KB)
|
|
| Determination of project specific tariff for 10.5 MW Small Hydro Power Project on Sarju River at Kapkot, Bageshwar District, Uttarakhand under Sections 62 and 86 of the Electricity Act |
Accessible Version :
View(228 KB)
|
|
| Petition under Section 86 (1) (f) of the Electricity Act, 2003, for adjudication of the disputes between M/s Swasti Power Ltd and Uttarakhand Power Corporation Ltd. |
Accessible Version :
View(227 KB)
|
|
| Prior approval of “Capital Investment for Renovation & Modernization of 4 x 36 MW Chilla HEP” of UJVN Ltd. under Section 61 and 86 of the Electricity Act, 2003 read with the relevant regulations |
Accessible Version :
View(65 KB)
|
|
| Misc. App. No. 02 of 2015 1) Investment Approval for construction of 1. (2×25 MVA), 220/33 kV S/s Barham (Jauljivi) and 2. Construction of LILO line of one circuit 220 kV |
Accessible Version :
View(72 KB)
|
|
| Application seeking approval of the Fuel Charge Adjustment (FCA) to be charged from the consumers for the period from 01.01.2015 to 31.03.2015. |
Accessible Version :
View(228 KB)
|
|
| Petition seeking waiver and refund of penalty imposed by the Commission vide its Order dated 01.09.2005. |
Accessible Version :
View(63 KB)
|
|
| Petition under Section 86(1)(F) of the Electricity Act, 2003 for adjudication of the disputes between M/s Swasti Power Ltd. and Uttarakhand Power Corp. Ltd. |
Accessible Version :
View(83 KB)
|
|
| Increasing capacity of 220 kV sub-station SIDCUL, Haridwar from 2×80 MVA (132/33 kV) to 2×80 MVA (132/33 KV) + 1×50 MVA (220/33 KV). |
Accessible Version :
View(50 KB)
|
|
| Petition filed by M/s Bhilangana Hydro Power Ltd. for indemnification on account of loss caused due to delay in commissioning of transmission/evacuation system |
Accessible Version :
View(48 KB)
|
|
| Dispute between UJVN Ltd. and Uttarakhand Power Corporation Limited (UPCL) relating to payments. |
Accessible Version :
View(59 KB)
|
|
| Applications seeking approval of UERC on the Power Purchase Agreement between Uttarakhand Power Corporation Ltd. and Himalaya Hydro Pvt. Ltd., Regency Yamuna Energy Ltd. |
Accessible Version :
View(65 KB)
|