Miscellaneous Orders 2012
21.12.2012
in the matter of Petition filed by M/s. Him Urja (P) Ltd. seeking determination of tariff of its Vanala SHP. 
 	19.12.2012
Order in the matter ofApproval of Capital Investment under Para 11 of the Transmission Licence [Licence No. 1 of 2003].
AND
in the matter of
Application No. 931/PTCUL/MD/UERC dated 29.05.2012 for approval of SI (Transmission) Scheme filed by Power Transmission Corporation of Uttarakhand Limited
 
    19.12.2012
in the matter ofApproval of Capital Investment under Para 11 of the Transmission Licence [Licence No. 1 of 2003].
AND
in the matter of Application No. 581/PTCUL/MD/UERC dated 17.04.2012 for approval of PS (EHV) REC-VII filed by Power Transmission Corporation of Uttarakhand Limited.
 
 
    19.12.2012
Order in the matter ofSuo-moto proceedings initiated by the Commission for non-compliance by UPCL under UERC (Tariff and Other Terms for Supply of Electricity from non- conventional and Renewable Energy Sources) Regulations, 2010 and UERC (Compliance of Renewable Purchase Obligation) Regulations, 2010 and also on the Petition filed by UPCL for revision of Renewable Purchase Obligation due to difficulties faced in procurement of power from renewable power producers by it.
 
 17.12.2012
Order in the matter ofDispute between M/s Swasti Power Engineering Limited and Uttarakhand Power Corporation Limited arising out of the Power Purchase Agreement dated 03.07.2009.
 
 11.12.2012
Order in the matter ofdispute between M/s Bhilangana Hydro Power Limited (Bhilangana-III SHP) and Power Transmission Corporation of Uttarakhand Ltd., regarding the obligation to make payment of additional transmission charges for the alleged dedicated transmission network.
 
 04.12.2012
Order on approval of PS (EHV) REC-VI filed by Power Transmission Corporation of Uttarakhand Limited 
 06.09.2012
Order in the matter ofApplication for review of the Commission’s Order dated 14.02.2012 on the petition filed by M/s R.V. Akash Ganga Infrastructure Limited seeking amendments in Power Purchase Agreement executed on 21.08.2010 with UPCL.
 
 03.09.2012
Order in the matter ofRepresentation made by M/s. Sravanthi Energy Pvt. Ltd. for refund of Supervision charges of Rs. 45.32 Lac paid to Power Transmission Corporation of Uttarakhand Ltd.
 
 03.08.2012
Order on Bhilangana-III & UPCL reg. obligation to make payment of additional transmission charges for augmentation work 
 18.06.2012
Order on Application filed by UPCL seeking approval for the investment on the project covering installation of capacitor banks on 11 kV at 33 & 11 kV substations 
 	 
    12.06.2012
In the matter of M/s Bhilangana Hydro Power Ltd. Versus Uttarakhand Renewable Energy Development Agency (Respondent) and in the matter of: Representation of M/s Bhilangana Hydro Power Ltd. for REC Accreditation of Bhilangana–III project under Regulation 9 (3) of the UERC (Compliance of Renewable Purchase Obligation) Regulation, 2010 
 
    29.05.2012
OOrder in the matter ofDetermination of Average Pooled Cost of Power Purchase (APPC) for the financial year 2012-13 for fulfilment of requirement specified under UERC (Compliance of Renewable Purchase Obligation) Regulations, 2010
 
 
25.05.2012
Order in the matter ofPetition No. 14 of 2012 filed by UPCL regarding waiver and refund of penalty imposed by the Commission vide its Order dated 11.08.2005
 
 
02.05.2012
PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY 
 
30.04.2012
in the matter of Approval of Capital Investment under Para 11 of the Transmission and Bulk Supply Licence [Licence No. 1 of 2003]AND
In the matter of Power Transmission Corporation of Uttarakhand Limited 7-B, Lane No. 1, Vasant Vihar Enclave Dehradun
AND
In the matter ofApplication No. 522/MD/PTCUL/UERC dated 07/04/2012 filed by Power Transmission Corporation of Uttarakhand Limited in connection with protection of 15 nos. tower foundations of 132 kV Bindal-Majra Double Circuit line.
 
 16.03.2012
In the matter of Representation made by M/s Sravanthi Energy Private Limited regarding treatment of start up power from UPCL and commercial treatment of infirm power and also clarification sought by UPCL on the issue of start up power for testing and pre commissioning activities And UPCL 
 13.03.2012
In the matter of Determination of charges applicable on the customers seeking open access to intra State transmission and/or distribution system in accordance with UERC (Terms and Conditions of Intra State Open Access) Regulations, 2010 
 
    14.02.2012
In the matter ofClarification sought by UPCL on levy of 15% Surcharge on Continuous Process Industries vide their letter no. 145/UPCL/COM dated 21.01.2012. 
 14.02.2012
In the matter ofM/s. R.V. Akash Ganga Infrastructure Limited reg. amendments in the Power Purchase Agreement dated 21.08.2010 executed with UPCL in accordance with the provisions of UERC (Tariff and Other Terms for Supply of Electricity from Non-conventional and Renewable Energy Sources) Regulations, 2010 and also Removal of Difficulty (First) Order, 2010 dated 28.10.2010. 
 13.02.2012
In the matter of Uttarakhand Power Corporation Limited’s Petition seeking Commission’s approval on Average Pooled Cost of Power Purchase (APPC) for the financial year 2011-12 for fulfillment of requirement specified under UERC (Compliance of Renewable Purchase Obligation) Regulations, 2010 
 
		 
        
         
        