Close

    Miscellaneous Orders 2022

    29.11.2022

    In the matter of:
    Application seeking approval of the investment on the Construction of 33 kV line (Underground and Overhead Lines) in Haridwar and US Nagar District of Uttarakhand.
    AND
    In the matter of:
    Managing Director, Uttarakhand Power Corporation Ltd., Victoria Cross Vijeyta Gabar Singh Bhawan, Kanwali Road, Dehradun.
    ...........Petitioner

    english pdf

    21.11.2022

    In the matter of:
    Application seeking approval of the Commission on the draft Power Purchase Agreement for medium term power purchase between Uttarakhand Power Corporation Limited and M/s NTPC Vidyut Vyapar Nigam Ltd.
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd.
    ...........Petitioner
    and
    In the matter of:
    M/s NTPC Vidyut Vyapar Nigam Ltd.
    ...........Respondent

    english pdf

    15.11.2022

    In the matter of:
    Application seeking approval of the Fuel Charge Adjustment (FCA) to be charged from the consumers for the period from 01.10.2022 to 31.12.2022.
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd.
    ...........Petitioner

    english pdf

    11.11.2022

    In the matter of:
    Petition for approval of Draft Amended Metering Communication & Data Acquisition Requirements (MCDAR) for Intra-State Power System of Uttarakhand after incorporating amendments as per CEA (Installation & Operation of Meters) (Amendments), Regulations, 2019 & 2022 in pursuance to Regulation 8.1 of UERC (State Grid Code) Regulations, 2016 and Regulation 10 of UERC (Conduct of Business) Regulations, 2014.
    AND
    In the matter of:
    Power Transmission Corporation of Uttarakhand Ltd., ‘Vidyut Bhawan’, Majra, Dehradun.
    ...........Petitioner
    ANNEXURE-1
    english pdf

    11.11.2022

    In the matter of:
    Petition seeking determination of project specific tariff for 1.5 MW (2 X 750 kW) Dunao Small Hydro Power Station under Section 62 and 86 of the Electricity Act, 2003 read with Regulation 13 of Uttarakhand Electricity Regulatory Commission (Tariff and Other Terms for Supply of Electricity from Nonconventional and Renewable Energy Sources) Regulations, 2013.
    AND
    In the matter of:
    Uttarakhand Jal Vidyut Nigam Ltd. …
    ...........Petitioner
    &
    In the matter of:
    Uttarakhand Power Corporation Ltd.

    ...........Respondent

    english pdf

    10.11.2022

    In the matter of:
    Petition seeking utilization of 220 kV S/C dedicated transmission line of M/s Greenko Budhil HEP till 30.11.2022 or commissioning of 400 kV D/c Transmission line, whichever is earlier, for evacuating power from generating stations operating in Ravi Basin, Himachal Pradesh viz. SHP upto 31 MW and from 180 MW Bajoli Holi HEP upto 120 MW, using 2x315 MVA, 400/220/33 kV GIS Pooling Station at Lahal, 220 kV S/C transmission line from Lahal connecting to 220 kV side of S/s at Budhil HEP on the same Terms of Use (Alternative-A) as determined by the Commission vide Order dated 04.12.20202 read with Order dated 30.06.2021.
    AND
    In the matter of:
    1. Himachal Pradesh Power Transmission Corporation Limited
    2. Himachal Pradesh State Electricity Board Limited
    3. M/s GMR Bajoli Holi Hydro Power Pvt. Ltd.

    ...........Petitioners
    &
    In the matter of:
    1. Uttarakhand Power Corporation Ltd.
    2. M/s Greenko Budhil Hydro Power Pvt. Ltd.
    3. State Load Dispatch Centre, Uttarakhand (SLDC)

    ...........Respondents

    english pdf

    09.11.2022

    In the matter of:
    Petition for approval of Provisional Tariff for Vyasi Hydro Power Project (2x60 MW) under Section 62 and 86 of the Electricity Act, 2003 read with the relevant regulations and guidelines of the Hon’ble Commission.
    AND
    In the matter of:
    UJVN Limited, “UJJWAL”, Maharani Bagh, GMS Road, Dehradun.
    ...........Petitioner
    &
    In the matter of:
    Uttarakhand Power Corporation Ltd., Victoria Cross Vijeta Gabar Singh Bhawan, Kanwali Road, Dehradun
    ...........Respondent

    english pdf

    03.11.2022

    In the matter of:
    Suo-moto proceedings initiated by the Commission in the matter of Show Cause Notice issued vide letter dated 27.01.2022 and in the matter of non-compliance of the Commission’s directions issued during the meeting held on 21.08.2020 in the Commission’s office for reviewing the status of construction of Bill Collection Centres.
    And
    In the matter of:
    Non-compliance of the Commission’s directions issued during the meeting held on 28.04.2022 in the Commission’s office for reviewing the progress of capital works approved by the Commission for UPCL
    &
    In the matter of:
    Managing Director, Uttarakhand Power Corporation Ltd., Victoria Cross Vijeta Gabar Singh Urja Bhawan, Kanwali Road, Dehradun. .........Respondent
    english pdf

    19.10.2022

    In the matter of:
    Petition seeking approval for increasing the Continuous Supply Surcharge (CSS) as approved by the Commission in the Tariff Order for FY 2022-23.
    And
    In the matter of:
    Uttarakhand Power Corporation Limited. (UPCL)
    .........Petitioner
    english pdf

    19.10.2022

    In the matter of:
    Determination of additional surcharge in accordance with the provisions of UERC (Terms and Conditions of intra–State Open Access) Regulations, 2015 to meet the fixed cost of UPCL arising out of its obligation to supply electricity to the open access consumers for the period October 2022 to March 2023.
    And
    In the matter of:
    Uttarakhand Power Corporation Limited. (UPCL)
    .........Petitioner
    english pdf

    14.10.2022

    In the matter of:
    Waiver of Supervision charges for upgradation works of 220 KV D/C Mahuakhedaganj–Kashipur including LILO of SEPL by replacement of ACSR Zebra Conductor with high capacity ACCC Conductor to be executed by the Petitioner as per UERC order dated 05.03.2021.
    In the matter of:
    M/s Sravanthi Energy Private Limited
    Registered Office: 7th Floor, Block -B,
    Building Number 9, DLF Cyber City,
    DLF Phase III, Gurugram - 122 002,
    Haryana, India.
    .........Petitioner
    AND
    In the matter of:
    Power Transmission Corporation of Uttarakhand Limited
    Registered Office: Vidyut Bhawan,
    Saharanpur Road, Dehradun. .
    .........Respondent
    english pdf

    28.09.2022

    In the matter of:
    Petition filed by Shri Chandrakant Singh Rawat (Innovative Solutions) seeking deemed generation claims due to late connectivity of its 500 kW Solar Power Plant with the grid and due to loss of generation because of outages/interruptions of more than 50 hours in, a year.
    In the matter of:
    Mr. Chandrakant Singh Rawat (Innovative Solutions), 188/1 Vasant Vihar, Opp. Electricity Office, Dehradun.
    .........Petitioner
    AND
    In the matter of:
    1. Managing Director, UPCL, Victoria Cross Vijeta Gabar Singh Bhawan, Kanwali Road, Dehradun.
    2. Executive Engineer, Electricity Distribution Division, Bhagwanpur, UPCL, Haridwar. .
    .........Respondent
    english pdf

    27.09.2022

    In the matter of:
    Waiver of supervision charges for upgradation works of 220 KV D/C Mahuakhedaganj– Kashipur including LILO of SEPL by replacement of ACSR Zebra Conductor with high capacity ACCC Conductor as per UERC order dated 05.03.2021 made by Sravanthi Energy Pvt Ltd under Section 86 of the Electricity Act, 2003 read with Regulation 40 of the Uttarakhand Electricity Regulatory Commission (Conduct of Business) Regulations, 2014 and the relevant provisions of UERC MYT Regulations, 2018.
    In the matter of:
    M/s Sravanthi Energy Private Limited Registered Office: 7th Floor, Block -B, Building Number 9, DLF Cyber City, DLF Phase III, Gurugram - 122 002, Haryana, India
    .........Petitioner
    AND
    In the matter of:
    Managing Director, Power Transmission Corporation of Uttarakhand Limited (PTCUL), Vidyut Bhawan, Saharanpur Road, Dehradun, Uttarakhand .
    .........Respondent
    english pdf

    28.09.2022

    In the matter of:
    Petition seeking approval of the Commission on Deviation in Power Purchase Costs and Removal of Difficulty for allowing Recovery of Incremental Power Purchase Cost and compliance thereof to directives issued under Multi Year Tariff Order.
    In the matter of:
    Uttarakhand Power Corporation Ltd.
    .........Petitioner
    english pdf

    27.09.2022

    In the matter of:
    Revision in Miscellaneous Charges as approved vide UERC’s Tariff Order dated 31.03.2022 for FY 2022-23.
    And
    In the matter of:
    Managing Director, Uttarakhand Power Corporation Ltd. (UPCL), VCV Gabar Singh Urja Bhawan, Kanwali Road, Dehradun
    .........Petitioner
    english pdf

    19.09.2022

    In the matter of:
    Petition for review of the Commission’s Order dated 22.06.2022 on application for approval of draft Power Purchase Agreement for short term power purchase between Uttarakhand Power Corporation Limited and M/s NTPC Vidyut Vyapar Nigam Limited.
    In the matter of:
    Uttarakhand Power Corporation Ltd.
    .........Petitioner
    english pdf

    12.09.2022

    In the matter of:
    Petition seeking removal of difficulty in implementation of modified Time of Day metering as provided in clause 6.1.3.5 of the Tariff Order dated 31.03.2022 for FY 2022-23.
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd. .........Petitioner
    english pdf

    12.09.2022

    In the matter of:
    Unplanned and irregular load shedding/curtailment of power by Uttarakhand Power Corporation Limited during the period 01st of March 2022 to 30th June 2022 and being continued till date.
    AND
    In the matter of:
    M/s Galwalia Ispat Udyog (P) Limited, Narayan Nagar Industrial Area, Bajpur Road, Kashipur, Udham Singh Nagar. .........Petitioner
    &
    In the matter of:
    Managing Director, Uttarakhand Power Corporation Ltd. (UPCL), Victoria Cross Vijeta Gabar Singh Urja Bhawan, Kanwali Road, Dehradun .
    .........Respondent

    english pdf

    02.09.2022

    In the matter of:
    Application seeking approval of the Draft Power Purchase Agreement between Uttarakhand Power Corporation Limited and UJVN Limited for its Suringad-II Small Hydro Power Plant (2X2.25 MW).
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd. .........Petitioner
    AND
    In the matter of:
    UJVN Ltd.
    .........Respondent

    english pdf

    29.08.2022

    In the matter of:
    Application seeking approval of the Fuel Charge Adjustment (FCA) to be charged from the consumers for the period from 01.07.2022 to 30.09.2022.
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd. .........Petitioner

    english pdf

    25.08.2022

    In the matter of:
    Petition seeking adjustment of tariff for 5 MW Motighat Small Hydro Power Project of M/s Himalaya Hydro Pvt. Ltd., due to additional capital expenditure necessitated due to the catastrophic damage caused to the plant by the unprecedented natural calamity/flood (force majeure event) that occurred on July 2nd, 2018, under Section 61 and 62 of the Electricity Act, 2003 read with Regulation 14(7) of Uttarakhand Electricity Regulatory Commission (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) Regulations, 2018.
    AND
    In the matter of:
    M/s Himalaya Hydro Pvt. Ltd. .........Petitioner
    AND
    In the matter of:
    (Uttarakhand Power Corporation Ltd.
    .........Respondent

    english pdf

    25.08.2022

    In the matter of:
    Petition seeking adjustment of tariff for 5 MW Tanga Small Hydro Power Project of M/s Himalaya Hydro Pvt. Ltd., due to additional capital expenditure necessitated due to the catastrophic damage caused to the plant by the unprecedented natural calamity/flood (force majeure event) that occurred on July 2nd, 2018, under Section 61 and 62 of the Electricity Act, 2003 read with Regulation 14(7) of Uttarakhand Electricity Regulatory Commission (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) Regulations, 2018.
    AND
    In the matter of:
    M/s Himalaya Hydro Pvt. Ltd. .........Petitioner
    AND
    In the matter of:
    (Uttarakhand Power Corporation Ltd.
    .........Respondent

    english pdf

    22.08.2022

    In the matter of:
    Petition seeking grant of permission to connect 33 kV dedicated line from 15 MW Captive Solar Power Plant to the stepdown side of 132/33 kV switchyard of Kashi Vishwanath Steels Pvt. Ltd. at 33 kV level so that continuous support essentially required from the grid for reference voltage and frequency for synchronization of grid tied solar inverters be obtained.
    AND
    In the matter of:
    M/s Kashi Vishwanath Steels Pvt. Ltd., Narain Nagar Industrial Estate, Bazpur Road, Kashipur-244713 .........Petitioner
    AND
    In the matter of:
    (1) Uttarakhand Power Corporation Ltd. (UPCL), VCV Gabar Singh Urja Bhawan, Kanwali Road, Dehradun
    (2) Power Transmission Corporation of Uttarakhand Ltd. (PTCUL), Vidyut Bhawan, Majra, Dehradun
    (3) State Load Dispatch Centre (SLDC), ‘Vidyut Bhawan’, Majra, Dehradun
    (4) Uttarakhand Renewable Energy Development Agency (UREDA), Urja Park Campus, Industrial Area, Patel Nagar, Dehradun
    .........Respondents

    english pdf

    20.07.2022

    In the matter of:
    Non-compliance of Sub-Section 3 of Section 43 of the Electricity Act, 2003 and Regulation 3.3.3 (17) & Regulation 3.3.3 (19) of UERC (The Electricity Supply Code, Release of New Connections and Related Matters) Regulations, 2020.
    &
    In the matter of:
    Non-compliance of Commission's directions issued vide Commission's Order dated March 10, 2022 pertaining to delay in release of new L T connections.
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd., VCV Gabar Singh Bhawan, Kanwali Road, Dehradun.
    english pdf

    20.07.2022

    In the matter of:
    In the Matter of: Petition to relax/waive or vary the provisions of UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2007 and UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2013 whereby the penalty was imposed in the matter of delay in release of new LT service connections for the period of F.Y. 2008-09 to F.Y. 2018-19 and upto Aug-2019. [Petition No. 30 of 2020]
    &
    Petition for extension of time for compliance of directions given by Hon'ble Commission vide order dated 07.01.2020 passed in the matter of relaxing/waiving or varying the provisions of UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2007 and UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2013 whereby the penalty was imposed in the matter of delay in release of new L T service connections for the period of FY 2008-09 to FY 2018-19 and upto Aug-2019 and for suspension of Standards of Performance during the Covid-19 pandemic period and accordingly waive the requirement of submitting various periodical reports. [Petition No. 20 of 2020]
    And
    In the matter of:
    Uttarakhand Power Corporation Ltd., VCV Gabar Singh Bhawan, Kanwali Road, Dehradun.
    .........Petitioner

    english pdf

    20.07.2022

    In the matter of:
    Investment Approval of:
    (a) Work of Construction of 132 kV & 66 kV Bays and installation of 3x20 MVA, 132/66 kV Transformer at 132 kV Substation Simli.
    (b) Construction of 66 kV DIC LILa Line of 66 kV Karanprayag-Kothiyalsain line at 132 k V Substation Simli.
    And
    In the matter of:
    Power Transmission Corporation of Uttarakhand Limited (PTCUL)
    english pdf

    06.07.2022

    In the matter of:
    Payment of Penalty as per sub-section 3 of Section 43 of the Electricity Act, 2003 and sub-Regulation 12 of Regulation 5 of UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2007/sub-Regulation 14 of Regulation 5 of UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2013, Commission’s directions issued vide Order dated 05.07.2016, 09.05.2017 and Commission’s directions issued vide Order dated 17.01.2018.
    &
    In the matter of:
    Petition to relax/waive or vary the provisions of UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2007 and UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2013 whereby the penalty was imposed in the matter of delay in release of new LT service connections for the period of F.Y. 2008-09 to F.Y. 2018-19 and upto Aug-2019. [Petition No. 30 of 2020]
    And
    In the matter of:
    Petition for extension of time for compliance of directions given by Hon’ble Commission vide Order dated 07.01.2020 passed in the matter of relaxing/waiving or varying the provisions of UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2007 and UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2013 whereby the penalty was imposed in the matter of delay in release of new LT service connections for the period of FY 2008-09 to FY 2018-19 and upto Aug-2019 and for suspension of Standards of Performance during the Covid-19 pandemic period and accordingly waive the requirement of submitting various periodical reports. [Petition No. 20 of 2020]
    &
    In the matter of:
    Suo-moto proceedings initiated by the Commission in the matter of non-compliance of the Commission’s directions issued vide letter dated 01.11.2021 pertaining to submission of Periodical Reports as per provisions of the Regulations.
    And
    In the matter of:
    Uttarakhand Power Corporation Limited .........Petitioner

    english pdf

    22.06.2022

    In the matter of:
    Application seeking approval of the Commission on the draft Power Purchase Agreement for short term power purchase between Uttarakhand Power Corporation Limited and M/s NTPC Vidyut Vyapar Nigam Ltd. .
    In the matter of:
    Uttarakhand Power Corporation Limited .........Petitioner
    AND
    In the matter of:
    M/s NTPC Vidyut Vyapar Nigam Ltd. .........Respondent

    english pdf

    22.06.2022

    In the matter of:
    Application seeking approval of the Draft Power Purchase Agreement between Uttarakhand Power Corporation Limited and UJVN Limited for its Kaliganga-II Small Hydro Power Plant (2X2.25 MW).
    In the matter of:
    Uttarakhand Power Corporation Ltd. .........Petitioner
    AND
    In the matter of:
    UJVN Ltd. .........Respondent

    english pdf

    29.06.2022

    In the matter of:
    Petition for review of the Commission’s Order dated 31.03.2022 on True up for FY 2020-21,Annual Performance Review for FY 2021-22 and Annual Revenue Requirement for FY 2022-23.
    In the matter of:
    Uttarakhand Power Corporation Ltd. .........Petitioner

    english pdf

    27.06.2022

    In the matter of:
    Petition for issuing necessary directions to UPCL to withdraw invoices issued against the Petitioner imposing 25% additional Temporary Supply Tariff and issue revised invoices under RTS-5 consumer category.
    In the matter of:
    M/s Dhanshree Agro Products (P) Ltd. .........Petitioner
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd. .........Respondent

    english pdf

    27.05.2022

    In the matter of:
    Suo-moto proceedings in the matter of applicability of Rate Schedule RTS-4A, Agriculture Allied Activities in light of Hon’ble ATE Order dated 10.02.2022 in Appeal No. 339 of 2017.

    In the matter of:
    M/s Flex Food Limited & Ors. .........Petitioner
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd. .........Respondent

    english pdf

    09.05.2022

    In the matter of:
    Petition seeking utilisation of 220 kV S/C Dedicated Transmission Line of M/s Greenko Budhil Hydro Electric Project for evacuating power from Generating Stations operating in Ravi Basin, Himachal Pradesh viz. Small Hydro Electric Projects of upto 31 MW and from Bajoli Holi HEP of upto 120 MW, using 2x315 MVA, 400/220/33 kV GIS Pooling Station at Lahal, 220 kV S/C transmission line (1.8 km) from Lahal connecting to 220 kV side of S/S at Budhil HEP on the same Terms of Use (Alternative-A) as determined by the Commission vide its Order dated 04.12.2020 read with Order dated 30.06.2021.

    In the matter of:
    1. Himachal Pradesh Power Transmission Corporation Limited 2. Himachal Pradesh State Electricity Board Limited 3. M/s Bajoli Holi Hydro Power Pvt. Ltd. .........Petitioners
    AND
    In the matter of:
    1. Uttarakhand Power Corporation Ltd. 2. M/s Greenko Budhil Hydro Power Pvt. Ltd. 3. State Load Dispatch Centre, Uttarakhand (SLDC) .........Respondents

    english pdf

    05.05.2022

    In the matter of:
    Petition seeking extension of Control Period of the benchmark capital cost & generic tariff as approved by the Commission vide its order dated 11/05/2020, 30/09/2020 and 05/10/2020 till March 2023 for installation of Solar PV Power Plants under the scheme of Mukhyamantri Saur Swarojgar Yojna.

    In the matter of:
    Uttarakhand Renewable Energy Development Agency .........Petitioner
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd. .........Respondent

    english pdf

    05.05.2022

    In the matter of:
    Petition under Section 86(1)(e) and 86(1)(f) of the Electricity Act, 2003 seeking extension of time for commissioning of the Solar project of M/s Parihar Constructions.


    AND
    In the matter of:
    Petition under Section 86(1)(e) and 86(1)(f) of the Electricity Act, 2003 seeking extension of time for commissioning of the Solar project of Saraswati Devi.

    In the matter of:
    M/s Parihar Construction
    Saraswati Devi .........Petitioner
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd.
    Power Transmission Corporation of Uttarakhand Ltd.
    Uttarakhand New and Renewable Energy Development Agency .........Respondents

    english pdf

    04.05.2022

    In the matter of:
    Review of the Benchmark Capital Cost for Solar PV, Solar Thermal and Grid Interactive Rooftop & Small Solar PV Plants to be applicable for FY 2022-23 and onwards till reviewed/ revised by the Commission.

    english pdf

    26.04.2022

    In the matter of:
    Petition for Approval of consolidated DPR amounting to Rs. 843.724 Crore funded through ADB, assuming 90% grant in loan component for transmission projects under UTSDIP Scheme.
    AND
    In the matter of:
    Power Transmission Corporation of Uttarakhand Limited (PTCUL)
    english pdf

    23.03.2022

    In the matter of:
    Filing of Miscellaneous Petition, inter alia amongst other grounds concerning refund of Minimum Demand Charges (MDC)/ Late Payment Surcharge (LPS) charges by illegal disconnection and for determining whether Minimum Demand Charges/ Late Payment Surcharge can be imposed, if power supply is disconnected u/s 56(1), without proper and clear 15 days notice u/s 181 r/w Section 50 of The Electricity Act, 2003.
    AND
    M/s Uttaranchal Iron & Ispat Ltd. .........Petitioner
    &
    Uttarakhand Power Corporation Ltd. .........Respondents
    english pdf

    23.03.2022

    In the matter of:
    Petition under Section 86(1)(c), (e), (f) and (k) read with Section 30 of the Electricity Act 2003 and Regulations 41(1) of UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) Regulations, 2018 seeking permission of the Commission to connect the Petitioner’s Suringad (5 MW) small hydro plant from 33/11 Darati S/s of UPCL.
    In the matter of:
    Managing Director, UJVN Limited “UJJWAL”, Maharani Bag, GMS Road, Dehradun .........Petitioner
    AND
    In the matter of:
    1. Managing Director, Uttarakhand Power Corporation Ltd. (UPCL)
    2. Managing Director, Power Transmission Corporation of Uttarakhand Ltd. (PTCUL)
    3. M/s Himalaya Hydro Private Limited.
    .........Respondents
    english pdf

    22.03.2022

    In the matter of:
    Determination of additional surcharge in accordance with the provisions of UERC (Terms and Conditions of intra–State Open Access) Regulations, 2015 to meet the fixed cost of UPCL arising out of its obligation to supply electricity to the open access consumers for the period April 2022 to September 2022.
    AND
    In the matter of:
    Uttarakhand Power Corporation Limited. (UPCL) .........Petitioner
    english pdf

    10.03.2022

    In the matter of:
    Suo-moto proceedings initiated by the Commission in the matter of noncompliance of the Commission’s directions issued vide letter dated 01.11.2021 pertaining to submission of Periodical Reports as per provisions of the Regulations.
    &
    In the matter of:
    Petition for extension of time for compliance of directions given by Hon’ble Commission vide order dated 07.01.2020 passed in the matter of relaxing/waiving or varying the provisions of UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2007 and UERC (Release of New LT Connections, Enhancement and Reduction of Loads) Regulations, 2013 whereby the penalty was imposed in the matter of delay in release of new LT service connections for the period of FY 2008-09 to FY 2018-19 and upto Aug-2019 and for suspension of Standards of Performance during the Covid-19 pandemic period and accordingly waive the requirement of submitting various periodical reports.
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd., VCV Gabar Singh Urja Bhawan, Kanwali Road, Dehradun .........Petitioner
    english pdf

    10.03.2022

    In the matter of:
    Application seeking prior approval of the Commission on the draft short term Power Purchase Agreements between Uttarakhand Power Corporation Limited and M/s PTC India Ltd., M/s Tata Power Trading Company Ltd. and M/s NTPC Vidyut Vyapar Nigam Ltd.
    In the matter of:
    Uttarakhand Power Corporation Limited .........Petitioner
    AND
    In the matter of:
    M/s PTC India Ltd.
    M/s Tata Power Trading Company Ltd.
    M/s NTPC Vidyut Vyapar Nigam Ltd ...........Respondents

    english pdf

    10.03.2022

    In the matter of:
    Suo-moto proceedings initiated by the Commission in the matter of Noncompliance of the sub-Regulations 3.3.3(15), 3.3.3(16), 3.4.3(10) & 3.4.3(11) of the UERC (The Electricity Supply Code, Release of New Connections and Related matters) Regulations, 2020 in the matter of ‘Availability of Three Phase Energy Meters’. AND
    In the matter of:
    Uttarakhand Power Corporation Ltd., VCV Gabar Singh Urja Bhawan, Kanwali Road, Dehradun ...........Petitioner

    english pdf

    09.03.2022

    In the matter of:
    Application seeking approval of the Fuel Charge Adjustment (FCA) to be charged from the consumers for the period from 01.01.2022 to 31.03.2022.
    In the matter of:
    Uttarakhand Power Corporation Ltd. .........Petitioner
    english pdf

    23.02.2022

    In the matter of:
    Application seeking approval on the Power Supply Agreements signed between UPCL and M/s Solar Energy Corporation of India (SECI).
    In the matter of:
    Uttarakhand Power Corporation Ltd .........Petitioner
    AND
    In the matter of:
    M/s Solar Energy Corporation of India. ...........Respondent

    english pdf

    11.02.2022

    In the matter of:
    Suo-moto proceedings initiated by the Commission in the matter of Show Cause Notice issued vide letter dated 27.01.2022 and in the matter of non-compliance of the Commission’s directions issued during the meeting held on 21.08.2020 in the Commission’s office for reviewing the status of construction of Bill Collection Centres.
    AND
    In the matter of:
    Managing Director,
    Uttarakhand Power Corporation Ltd.,
    Victoria Cross Vijeta Gabar Singh Urja Bhawan, Kanwali Road, Dehradun ...........Respondent

    english pdf

    03.02.2022

    In the matter of:
    Application seeking prior approval of Hon’ble Uttarakhand Electricity Regulatory Commission on the Power Purchase Agreement to be executed between UPCL & UJVN Ltd for Vyasi HEP (120 MW).
    In the matter of:
    Uttarakhand Power Corporation Ltd. .........Petitioner
    AND
    In the matter of:
    UJVN Ltd. ...........Respondent

    english pdf

    03.02.2022

    In the matter of:
    Application seeking approval on the two Draft Power Purchase Agreements proposed to be entered into between UPCL and M/s Sravanthi Energy Pvt. Ltd & M/s Gama Infraprop Pvt. Ltd.
    In the matter of:
    Uttarakhand Power Corporation Ltd. .........Petitioner
    AND
    M/s Sravanthi Energy Pvt. Ltd..........................Respondent No. 1
    M/s Gama Infraprop Pvt. Ltd. ..........................Respondent No. 2
    english pdf

    21.01.2022

    In the matter of:
    Application seeking prior approval of the Commission on the draft Power Purchase Agreement between Uttarakhand Power Corporation Limited and M/s PTC India Ltd. on short term basis.
    In the matter of:
    Uttarakhand Power Corporation Limited .........Petitioner
    In the matter of:
    M/s PTC India Ltd. ...........Respondent

    english pdf

    17.01.2022

    In the matter of:
    Petition seeking utilisation of 220 kV S/C dedicated Transmission Line of M/s Greenko Budhil Hydro Electric Project for evacuating power from small hydro projects operating in Ravi Basin, Himachal Pradesh of upto 26 MW and from Bajoli Holi HEP of upto 60 MW by connecting 2x315 MVA, 400/220/33 kV GIS Pooling Station at Lahal to 220 kV side of S/S at Budhil HEP on the same Terms of Use (Alternative-A) as determined by the Commission vide its Order dated 04.12.2020 read with Suo-moto Order dated 30.06.2021.
    In the matter of:
    1. Himachal Pradesh Power Transmission Corporation Limited
    2. Himachal Pradesh State Electricity Board Limited
    3. M/s Bajoli Holi Hydro Power Pvt. Ltd.
    .........Petitioner

    AND
    In the matter of:
    1. Uttarakhand Power Corporation Ltd.
    2. M/s Greenko Budhil Hydro Power Pvt. Ltd.
    3. State Load Dispatch Centre, Uttarakhand (SLDC)
    english pdf

    03.01.2022

    In the matter of:
    Application seeking approval for the investment on the project covering the construction of 03 No. 33/11 kV Substations alongwith their associated 33 kV Line and 33 kV Line from Solar Power Generator’s Switching S/s Kafaltana to 33/11 kV S/s Deghat.
    AND
    In the matter of:
    Uttarakhand Power Corporation Ltd., VCV Gabar Singh Bhawan, Kanwali Road, Dehradun. .........Petitioner

    english pdf